Question 1097 of 731 · Texas Journeyman Electrician Exam
The point of connection between the facilities of the serving utility and the premises wiring is called the:
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1097
- A: Service point
Explanation
Article 100 defines the service point as the point of connection between the facilities of the serving utility and the premises wiring. Everything on the load side is premises wiring covered by the NEC.
More questions: Definitions, Theory and Plans
- 1098A partially protected location under a canopy or a roofed open porch is classified in the NEC as a:
- 1103NEC 110.3(B) requires that listed or labeled equipment be installed and used:
- 1104Unless the equipment is listed and marked otherwise, terminations for circuits rated 100 amperes or less (or 14 AWG through 1 AWG conductors) are based on which conductor temperature rating?
- 1105For circuits rated over 100 amperes, or conductors larger than 1 AWG, terminations are generally based on which conductor temperature column?
- 1106Copper and aluminum conductors may be joined in the same terminal or splicing connector only when:
- 1108The required depth of working space in front of a 120/240-volt panelboard (150 volts or less to ground) is, for all conditions: