A commercial building's 1-year maximum demand is 160 A. Using the NEC 2026 existing installation method, what is the load before new loads are added?

Exactly one answer is correct.

Show solution

Correct answer to question 12076

  • D: 200.0 A

Explanation

Where maximum demand data for one year is available, that value is taken at 125 % (120.87): 160 x 1.25 = 200 A. The new load is then added to that figure.