Question 2015 of 850 · Texas Journeyman Electrician Exam

Under the 2023 and 2026 NEC, when is surge protection required for an existing dwelling service?

Exactly one answer is correct.

Show solution

Correct answer to question 2015

  • B: When the service equipment is replaced

Explanation

Starting with 2023, 230.67 applies when service equipment is replaced, not only to new services. A meter change by the utility does not trigger it. See 230.67.

Next to question ›